Our Construction
Plan
Our 25-step precision roadmap ensures structural permanence and quality at every stage.
25-Step Roadmap
From virgin site to masterwork handover.
Foundation & Prep
Site cleaning, leveling, layout marking, excavation, and PCC bed preparation.
Structural Plinth
Footing concrete, column starter, RR masonry to plinth, and plinth beam casting.
Superstructure I
Wall construction to lintel height, lintel beam casting, and electrical conduit routing.
Roofing & MEP
Roof slab shuttering, reinforcement, casting, curing, and plumbing rough-ins.
Finishing & Handover
Plastering, flooring, painting, fixture installation, and final site clearance for handover.
Every Step, Documented.
Site cleaning – JCB / Labour.
Server marking.
JCB Excavation.
Cleaning of putty and PCC (40mm Jelly).
Server marking.
Column steel work and carpenting work.
Pillar and mat fixing.
Laying of concrete.
Pedal straps shuttering and concrete.
Soil backfilling again.
Plinth excavation with bottom PCC.
Plinth bar bending.
Shuttering.
RCC plinth concrete.
Brick work (Lintel Level).
Bar bending and shuttering (Lintel and Charpija).
Roof level brick work.
After shuttering and bar bending work and electrical and concrete slab.
15 days of curing.
Parapet wall.
Inner and outer grouting and electrical box.
Doors and windows.
Painting – 2 putty, 1 framer and 2 painting.
External framer – 1 quoting, 2 quote painting.
Inside wood work full polish.
Timeline Required
Timelines are subject to environmental conditions and material curing cycles.